Academic year 2002-2003
UNIVERSITY PARIS X- NANTERRE
_________________________________
D.E.S.S. Right of the International Trade
Debbie Danoffre
Development of the Financing of Project and
Privatization in the Arab Peninsula
MR PATRICK BLANCHARD,
Financing of Project
Privatization is defined as the transfer of the goods, or the
responsibility of a service, governmental control towards the private
company. Primarily, it is acted well in fact of transferring the commercial
risk towards the private sector. The consequence of such a transfer is that it
is accompanied by a symmetrical transfer by control and decision-making towards
private organizations. Political perceptions, as much as the inescapable
consequences in social and economic terms bring the governments to a great
prudence before slackening their control completely. This is why, with the
Middle-East, privatization is carried out only by stages during which, at least
at the beginning, the government maintains a level of undeniable framing in the
catch of the decisions.
Project Financing, or financing of project, is
generally included/understood as being the financing of a project in which the
financial organizations are based on the incomes generated by the exploitation
of the project for « to guarantee » the refunding of their
loans1(*). Without being
unaware of the identity of the future shareholders (sponsors), one can
say that the organizations lenders are based much more on the economic and
industrial feasibility of the project that on the assessment or the merits of
the aforesaid shareholders.
Since the middle of the Nineties, the Middle-East opened in
the world of the financing of project. Insofar as the legal environment and the
rules governing the creation of companies evolve/move and improve, the banking
world more was interested in this type of financing in the area. Indeed, the
States started to show a keen desire to draw aside their assessments certain
great projects of public interest, and the Middle-East at once became the
favorite hunting ground of the international financial organizations. Between
the financings of already closed projects and those which are under
development, the work-in-progress Project Financing rises today with
nearly 90 billion dollars US.
This is particularly true in the fields of oil, gas, and
electricity. The governments are increasingly reticent to engage the mobilizing
government stocks in great projects of heavy capital, particularly because of
the variations of the price of the oil barrel, and thus of the incomes coming
from oil. They thus launched out in the search for private means of financing.
It does not have them escaped that the financing of project makes it
possible to the sponsors to decrease their general exposure by
transferring certain project risks towards other parts.
This memory concentrates more particularly on the
privatization and the development of the financing of project to the
Middle-East in the field of the production of electricity. In the years which
come, one expects in this sector has a growth without precedent, and with
corresponding investments in all the area, because the governments try to
diversify and relieve an economy primarily based on oil. The need for power
electric is the determining factor of the evolution towards the privatization
of the manufacturing units and the intervention of producers independent of
electricity (IP2(*)) and
water (IPWP3(*)).
The programmes of privatization under development to the
Middle-East proceed in general of a common strategy. It is characterized by a
progressive transition from a monopoly of state (often heavily subsidized)
towards the private property (and thus hoped profitable) of the means of
production. The best means of illustrating the evolution of the financing of
the IP to the Middle-East consists in examining the efforts made in the
direction of privatization by Abou Dhabi, Jordan and Saudi Arabia.
Abou Dhabi : the regional leader for the
privatization of electricity
Abou Dhabi, the main thing of the seven emirates4(*) which constitute the United Arab
Emirates, continues to be the regional leader for the reorganization and the
privatization of the sector of the production of electricity. It is Giat
Industries which, during its work to try to discharge Offset obligation
contracted at the time of the sale of 436 Leclerc tanks to the Emirates, (but,
as would say Kipling, this is another history), proposed the idea of
privatization, carried out feasibility studies thorough on the Mirfa power
stations then of Taweelah B, and produced in 1994 and 1995 of and the text
draft agreements of law allowing the installation of such a privatization. The
business was alas without a future for Giat Industries, but colossal produced
work constitutes still today the base of the programme of privatization in the
emirate.
Indeed, in 1996, Abou Dhabi began its program by the
publication from the Decision N° 1, which created the Committee of
Privatization of the Sector of Water and Electricity. After completion of work
of the Committee, Deputy Ruler, Sheik Khalifa bin Zayed Al Nahyan,
enacted the Decree of the Emir N°. 7 of 1997 which establishes the idea of
operation of the government to arrive at the reorganization and privatization.
It was about :
1. To then share the properties of the organization of state
in load, the Toilets and Electricity Department (WED) between separate
and distinct entities, this being accompanied by the transfer of some of the
interests of these entities towards private investors,
2. To into force develop and put a new legal and lawful
framework,
3. To satisfy the needs envisaged in terms for water and
electricity through projects in form IPWP. 5(*)
In February 1998, the WED was replaced by ADWEA (Abu Dhabi
Water and Electricity Authority). The flow chart of ADWEA is shown in the
following page. ADWEA immediately created a subsidiary company, ADWEC (Abu
Dhabi Water and Electricity Company), which remains the exclusive
supplier/purchasing of produced water and electricity. ADWEC is also
responsible to establish projections in terms of need for output, which matches
of a responsibility in the establishment of the invitations to tender allowing
creation for new IPWP. Lastly, ADWEC is the central merchandizing of gas
necessary to the operation of the electricity/manufacturing units water.
The role of ADWEC consists in buying water and electricity at
certain independent companies (of which the IPWP) through in the long run
called contracts of purchase PWPA (Power and Water Purchase
Agreement). ADWEC then sells water and electricity at two distributive
firms through TRANSCO, governmental company of transmission of water and
energy.
This sale is carried out according to a tariff « in
bulk and wholesale », but which includes/understands the cost of the
generation, the operating costs of ADWEC, and the cost of the transmission. The
companies of distribution must then establish a tariff (not subsidized)
applicable to the end-user, tariff which must be based on « economic
cost », which includes the price invoiced by ADWEC, increased cost of
the distribution.
D. Danoffre 1999

In theory, the subsidies granted by the government are
carried out only through one refunding poured directly by the State with
certain groups of customers. A company of independent regulation supervises the
correct operation of the companies lately create and the calculation of the
tariffs.
Since 1998, competition was actually introduced into the
activities of production of water and electricity. Three projects IPWP up to
now reached the installation of Project Financing : Taweelah A2 in 1999
(CMS), Taweelah A1 in 2000 (TOTAL & Tractebel) and Shuweihat 1 in 2001 (CMS
& International Power).
Although ENRON and consortium TRACTEBEL/TOTAL, led by the
Belgian group, were a long time in the group of head, it is with American group
CMS Energy Corporation that Taweelah A2 was allotted in
October 1998. It was about first project IWPP in the world, which represented
an amount of about 760 million dollars6(*). The financing, assembled under
the leadership of the leader BARCLAYS BANK, was accomplished
with a delay, considered acceptable, six months compared to the initial
objectives. It was about one « dry credit », i.e. without
participation of the agencies of credit export, one 17 years duration (a record
for L `time7(*)). It
did not comprise cash a sweep8(*) (mechanism outrageusement favorable for the lenders)
and thus excluded the risks from obligation of refinancing or not-payment of
dividends, because the government wished to draw up a new point of long-term
reference for the attribution of loans in the country. On the other hand, the
system included/understood one « security
package » resting mainly on the goods and incomes of the
company-project, like on direct agreements signed by the bankers with the Joint
Venture selected to build the factory turn-key9(*) and with the company in charge of the exploitation of
this one10(*).
But it is well following privatization, Taweelah
A1, gained this time in May 2000 by consortium TOTALFINAELF/TRACTEBEL,
led by Middle East Management of the French tanker, which opened new grounds
with the Middle-East for the financing of project. It was about a project of
the form build-own-operate, or BOO, which included/understood the
restoration, the handing-over with technical height and the extension of an
existing factory producing of electricity and water freed of salt in order to
obtain an installation able to produce at least 1430 MW and
84 MIGD11(*)
(approximately 25% of the needs for the emirate in terms of water and
electricity).
The transaction contained gravitational financial terms
equivalent to those which could have been found in Europe for a business of the
same type, which means that they were quite higher than those available at the
time on the American money market. For one
« deal » total of 1,4 billion
dollar, the financing amounted to 1,015 billion (ration debt/equity
75 : 25), for the one duration of 18 years and half, longest in the area.
There still, the agencies of credit export missed device, which was, him also,
a first with the Middle-East : the banks (leaders : BNP
Paribas and CITYBANK) admire that the shareholders
pour their contribution in own capital stocks only after the complete pulling
of the banking commercial debt12(*). The conditions were so interesting that the loan was
sursouscrit with 250% at the time of the international syndication. Several
local banks took part in this syndication, and in particular National
Bank off Abu Dhabi and Abu Dhabi Investment
Corporation. The fact deserves to be announced as a mark of progress
of the financing of project to the Emirates because, before, the local banks
agreed of the loans only in exchange of personal guarantees provided on their
own goods by the borrowers. To also note that it is the project Taweelah A1
which set up the contractual system of escrow account13(*) (for the payment of the price
authorized for the purchase of the existing factory), which functioned so that
it became one of the contractual bases in the book of invitation to tender
emitted for the fourth privatization, Umm Al Nar. The financial engineering of
Total Fina Elf for the project Taweelah A1obtint six international prices,
decreed by the financial press, whose «Project Finances Deal off the
Year» (Euroweek), «Power Deal off the Year»
(International Project Finance), «Middle East and Africa Deal off the
Year» (Project Finance Magazine), «Emerging Markets Deal off
the Year» (Euromoney).
It is in December 2001 that the financing of following
privatization, Shuweihat 1, goal definitively
« buckled ». It was about a factory grassroot BOO of 1500
MW and 100 MIGD to be built in the extreme West of the emirate, with 250
kilometers of the capital, which was allotted to the consortium between
CMS Energy (the USA) and International Power (the
U.K.). At an overall cost of about 1,6 billion dollar, the financing to be
obtained rose at 1,285 billion over one duration 20 years. Its
syndication, impetus says one the day before September 11, 2001, was largely
disturbed by the events which one knows. However, thanks to the more or less
underground support provided by the ADWEA, and to the appearance of a
substantial portion of Islamic financing, the banks14(*) ended up following. The
project obtained even the prices « Project off the Year »
(MEED) and « Middle East Power and Deal Toilets off the
Year » (Euromoney Project Finances).
In these three cases, the government retained the majority to
a total value of 60% of the shareholding, and hears privatiser gradually this
share by offers of sale (IPO, or « Initial Offerings
Public ») reserved to the citizens of the E.A.U.
While at the same time the duration of the loans authorized
for these businesses was greeted like a mark of the maturity reached by the
market, about many financial organizations are worried by the growing appetite
of the area for so long terms. Indeed, this appetite could more be able to be
satisfied, taking into account the number of the transactions until one waits
in a future close relation. A British leader of one of the large banks of the
Golf observes that if one continues with « to push » of the
businesses in financing « without envisaging a refinancing at the end
of ten or twelve years, the building will break down ». 15(*)
Currently, Abou Dhabi is in the last phase of privatization of
the factory Umm Al Nar (« Mother of Fire »)
including/understanding the repurchase of certain existing units for an amount
which, according to International Power, would exceed
the billion dollar, while at the same time the estimate of its
competitor TOTALFINAELF would show a clear residual value of
about 670 million dollars...
TOTALFINAELF proposes a financing, completely
subscribed16(*), of a
traditional type from now on : 1,35 redeemable billion
dollar over 20 years as from the commercial starting of the factory,
ratio debt/equity 75 : 25 being able to reach 80 : 20 if the real
costs of the project are reasonable. It is in fact the first offer with the
complete financing received until now by ADWEA. Moreover, the Islamic financing
could be actuated with height of 200 million dollars by Abu Dhabi Islamic Bank
and 300 million per National Bank off Abu Dhabi.
International Power has a more complex structure, but also
more « fuzzy » in the duration. It
includes/understands :
1. a facility of short-term, to allow the payment of the
existing installations, redeemable treasury from June 2006 to June 2008,
2. A bridge loan for the share normally to pay in own capital
stocks, refinançable in June 2008,
3. A 20 years loan (not subscribed) redeemable as from
December 2008.
The decision of ADWEA should intervene during March 2003... if
the Iraqi question allows it.
|
Electric outputs installed with Abou Dhabi
|
|
Company Owner
|
Machine
|
MW
|
|
% of the foreign share (40%)
|
|
|
|
|
CMS
|
Int' L Power
|
TFE
|
TBL
|
|
Shuweihat CMS Int' L Power.
|
Shuweihat 1
|
1500,00
|
|
60,00%
|
40,00%
|
|
|
|
GTTPC
|
TAW A1
|
1430,00
|
|
|
|
50,00%
|
50,00%
|
|
Taweelah Power Corporation
|
TAW B
|
1069,00
|
|
|
|
|
|
|
Umm Al Nar Power Company
|
Umm Al Nar
|
1215,00
|
|
|
|
|
|
|
Emirates CMS Power
|
TAW A2
|
763,00
|
|
100,00%
|
|
|
|
|
Baynunah Power Company
|
Al Ain
|
426,00
|
|
|
|
|
|
|
RASCO
|
Remote Areas
|
286,00
|
|
|
|
|
|
|
Mirfa Power Company
|
Mirfa
|
246,00
|
|
|
|
|
|
|
Mirfa Power Company
|
Madinat Zayed
|
134,00
|
|
|
|
|
|
|
Baynunah Power Company
|
Abu Dhabi
|
533,00
|
|
|
|
|
|
|
Umm Al Nar Power Company
|
Banyas
|
120,00
|
|
|
|
|
|
|
Total Capacities Megawatts
|
|
7722,00
|
|
|
|
|
|
The privatization of the distribution and the transmission is
much less advanced. The regional companies of distribution are authorized to
practice only one very limited competition and until now no private investor
was solicited. As for the transmission, it remains, at least for the moment,
the monopoly « naturalness » of the state. Because it is
well this monopolistic position of the government which allows him to be
established like the intermediary of right between the firms of production and
the companies of distribution, and also to preserve a narrow control on the
level of the granted subsidies, not to even say on their existence.
Jordan : establishment of the foundations allowing
the reform of the structures
The programme of privatization of Jordan, much less mature
than that of Abou Dhabi, follows from there less one very similar model :
the government remains exclusive purchaser of energy, the transmission falls on
companies of state, but the production and the distribution must be gradually
privatisées.
Being more particularly the field of the production of
electrical energy, Jordan Electricity Sector Report published in
January 2001 estimated that Jordan would need more than 10.000 GWh to satisfy
the electric demand for 2005, and 12.500 GWh around 2010, is respective
increases in 34% and 65% compared to the production of 2000.
In 1999, in order to prepare privatization, the government
replaced the law of 1996 by the news General Electricity Law n° 13. The
same year, the national company in load of the production of electricity NEPCO
(National Electric Power Company) was separate into three :
NEPCO, CEGCO (Central Electric Generating Company) and EDCO
(Electric Company Distribution).
NEPCO, which remains state-owned property, deals of the
direction, the exploitation and the development of the distribution network
high voltage, the control system and the regional grid. It is this entity which
is the single purchaser.
CEGCO is the principal company of Jordanian production ;
it should be privatisée in the short run. EDCO should follow the same
way ; it is responsible for the distribution of electricity outside the
concessions granted to Jordan Electric Power Company (JEPCO) and
Irbid Distribution Company (IDECO). The process of privatization of CEGCO
and EDCO timidly started with semi-2002, whereas it began in 2001 for IDECO,
whose government wishes to give up 55 to 70%. It should be noted that the
privatization of these companies is a condition posed by the International
Monetary International Monetary Fund with the extension of the facilities
granted to Jordan.
The tariffs of electricity were fixed in May 1996, but taking
into account the trend of the price of the oil barrel, the government had to
re-examine them since 2001. The tariff applicable to the distributive firms
should increase, and be reflected then towards the end-user.
The bases were thus thrown. In May 2000, the Jordanian
government chooses as a preferred bidder for the development and
construction in BOO of the first IP of the country. The negotiations with the
Belgian group had already trailed during years, primarily because of
uncertainties related to the origin of gas necessary to the production. Located
with Kherbet-Al-Samra, the factory was to have a capacity of 450 MW. Until
2002, the Jordanian government and TRACTEBEL negotiated certain aspects of the
project, including the terms of financing, in the hope to concretize it during
2003. The business, in any event, could hardly progress without the
construction of a suitable pipeline. Unfortunately, on the instructions of its
SUEZ shareholder, TRACTEBEL, which had already given up depositing an offer for
the business of Umm Al Nar in Abu Dhabi a few hours before the opening of the
folds, gave up the Jordanian business abruptly.
In addition to the vexations of SUEZ because of hazardous
investments in the field of the water treatment, one can guarantee, there
still, that the situation in Iraq is not foreign with this withdrawal. All this
of course has very negative effects on the credibility of Jordan and
discourages the financial organizations which, otherwise, could have invested
in the sector, which shows, but this time in a negative way, the close
connection which exists between the privatization of the sector and the
development of the financing of project.
Saudi Arabia : a step front, two steps
behind !
The electric developers of projects constantly scan the
efforts made laboriously by Saudi Arabia (KSA) to reform the sector in
question. The country presents great potentialities for the blooming of the
IP : it is estimated that, if KSA wishes not to be overflowed by the
increase in the electric request in the country, its need for investment on the
matter will reach the 117 billion dollars in the twenty years
to come. This represents an increase in the working installed capacity of the
order 50.000 Megawatts. The electric policy of KSA is far from being as well
defined as that of Abou Dhabi, but it does not present of it less the budding
of the same strategy :
1. separation of the goods of the State between generation,
transmission and distribution
2. adherence with the concept of the government as an
exclusive purchaser.
However, certain events which proceeded into 2000 bring to
wonder about the sincerity of the Saoudi government (monarchy
« lit » ?) in its search of privatization and reform.
Indeed, the will of the government appeared to weaken when in October 2000 it
succumbed to pressures of the public by cancelling increases in tariff decided
by Saudi Electricity Company (SEC) in April. However, this increase in tariff
had been decided in order to make it possible future the IP to function with a
rate of return reasonable and this without guaranteed governmental subsidies
nor dividends.
Moreover, legal environment and
« operational » Saoudi is underdeveloped, while at the same
time the government feels reluctant to provide guarantees, which presents
obstacles more than significant at the development of the privatization of the
sector of electricity. The factory of Shuaiba, for example, of a cost
of 2,2 billion dollars, owed at the origin being a IP. But the
private investors were not interested in it, precisely because of their doubts
about the stability of the tariffs and the applicable legal status.
Consequently, the project was financed by the government on an Islamic basis
provided by Al-Rajhi Banking and Investment Corporation.
In spite of that, KSA continues to push new diagrams of
financing for its electric projects. For example, station PP9 (1200MW) in the
north of Riyadh was financed by excesses of incomes taken on the large-scale
consumers since 1995. The factory Ghazlan II (2400 MW) is financed through a
loan of 500 million dollars, trade unionist to the
international one, and who gives to his transmitters the right to refund
himself if need be on request starting from the incomes of prestigious
customers such as Saudi Aramco. Another test tried by KSA to show its sincerity
lay in the project of a IP « captive » of 320 MW that Saudi
Petrochemical Company envisaged to create to satisfy its own needs. Americans
ENRON and CMS Energy had been selected like foreign partners... The scandalous
bankruptcy of the first, the failure and the withdrawal of the second, and
finally the events of September 11, 2001, were to strike of a fatal blow this
attempt, with the remainder not very convincing.
The financial organizations remain in active day before. But
nothing will be possible as long as the Saoudi government will not have shown
its political capacity to impose not subsidized tariffs and tallies legal and
operational transparency. This, without forgetting that the question of the
development of the gas fields, necessary to the electrical power, remains
outstanding, whereas it is probably the only reason which brings them
« large »17(*) with still considering the subject in Saudi
Arabia.
Conclusion
The governments of the Arab peninsula, to differing degree
appear to have admitted that their loathing to grant sovereign guarantees moves
away the investors who are neither of the agencies of credit export, nor of the
multilateral institutions. Although it is exact that privatization implies the
creation of independent entities capable of self-sufficiency, it would not be
reasonable to expect that the developers enter the eyes closed and without
support new companies which do not have any countable history nor operational.
So that such a project meets success, it is appropriate that the risks and
profits are equitably distributed between the government concerned and the
private investors.
The evolution of the structures of financing of the IP in the
area shows well the increase in the interest and confidence tested by the
financial organizations. The participation of the agencies of credit export is
not any more one indispensable condition. Even if privatizations of Abu Dhabi
showed that long-term loans can be secured, it does not remain about it less
than, so that the financings perdurent, it will be necessary that the area
shows its capacity to extend the depth and the diversity of its sources of
financing.
Or else, the international banks will end up reaching the
limit of their exposure per country, and the developers will have to be
addressed elsewhere to finance or refinance the debt of the projects. The
solutions of replacement, in terms of financing, will include/understand then,
most probably, the capital markets (projects jumps) the Islamic financing and
the regional banking market.
But all this will not be able to be carried out, as we believe
to have shown it through the example of Abou Dhabi, that if the governments
concerned show their adherence with the process of privatization by the setting
does not place and in force of transparent lawful structures and disciplined
tariffs.
Or else, the process will be put in danger, and the flood of
the investments and the financings will be dried up irremediably.
BIBLIOGRAPHY
Ø The Guides To Financing International Oil and gas
projects, Milbank, Tweed, Hadley & McCloy- 1996
Ø Project Finances International Yearbook 1999
Ø Particular reports/ratios Electricity, Total 1998,
Total Fina Elf 2000/2002.
Ø Middle East Economic Digest, since October 1999
Ø The Website for the Power Industry (
http://www.power-technology.com)
Ø Jordan Electricity Sector Carryforward, January
2001
Ø Website of the embassy of Jordan.
Ø Energy Intelligence Briefing, 18/02/2003
* 1 Guide for the Financing of
the International Projects Oil and Gas, Milbank Tweed
* 2 Independent Power
Producer
* 3 Independent Power and
Producer Toilets
* 4 Abu Dhabi, Dubai, Sharjah,
Ajman, Fujeirah, Close-cropped Al-Khaimah and Umm Al-Qwain.
* 5 MEED, Special Abu Dhabi
Carryforward, 20/02/1998
* 6 for 710 megawatts (MW) and
50 million Imperial gallons per day (MIGD)
* 7 until this moment, one
considered that for the area one 12 years duration was extremely ambitious.
* 8 as under consideration at
the origin in this case : all the funds of the company are regularly
transferred firstly at the organization lender. The possible distribution of
dividends is done only then. The requirements in working capital are the
subject thus of separate financings.
* 9 Siemens/Hanjung .
* 10 in fact, a subsidiary
company of CMS created of any part to this end, in order to maximize the rate
of return of the Americans.
* 11 I.e. 380.000 tons of water
per day !
* 12 « back ended
equity » : this system can be adopted only if the shareholders
have a very strong credit.
* 13 count of setting in third
hand
* 14 Capital Barclays,
Citibank, Bank off Tokyo-Mitsubishi, Kreditanstalt fur Wiederaufbau, Royal Bank
off Scotland, National Bank off Abu Dhabi, Abu Dhabi Investment Company,
Crédit Lyonnais, HSBC Investment Bank, Sumitomo Mitsui, Abu Dhabi
Islamic Bank.
* 15 Mr. E.E.D, October 2000
* 16 by ABN Amro, Crédit
Lyonnais, Royal Bank off Scotland, etc
* 17 Exxon Mobil, Shell,
TotalFinaElf, etc
|